Sunday, August 5, 2012

A view from the water tank . . . or there abouts

A friend suggested taking a photo from the same spot at different times during our build.  So here is the first one, with many more to come below!


Wednesday, 25th July 2012

waiting for work to start...

Thursday, 16th August 2012

 
House pad cut


Friday, 17th August 2012


House pegged out, but pretty hard to see blue markings

Monday, 20th August 2012



Under slab drainage and power run to the house


Tuesday 21st August 2012


Footings dug

Wednesday, 22nd August 2012

Today a portaloo was delivered and put right in my view from the tank.  Didn't they know that was 'my spot' to take progressive photos?  So future photos will be from wherever looks good...


Form work and waffle pods set up

 Thursday, 23rd August 2012


Slab poured


Thursday, 30th August 2012


Lower frame


Friday, 31st August 2012

Upper frame

Monday, 3rd September 2012


Scaffolding down, lower roof framing completed, front porch posts & roof goes up


Thursday, 6th September 2012


The roof trusses are on!